Project Overview
The new facility will allow consolidation of the School of Pharmacy’s programs on the Anschutz Medical Campus, in a location ideally suited to serve students; support faculty scholarly activity and research; and enhance collaborative work with the other schools of the Anschutz Medical Campus and companies in the developing biotech park. It will allow the expansion of the faculty who provide pharmaceutical education, research and patient care and who prepare students for their roles as pharmacists and pharmaceutical scientists. This facility is on track to be the first University of Colorado Denver LEED certified building with an anticipated Silver rating, possibly Gold.
Project Manager
Kathryn McNally, 303-724-0755
Doug Derber, 303-724-1032
Project Architect
HOK, Denver and St Louis offices
General Contractor
M.A. Mortenson Company
Gross Square Footage
171,000
Project Cost
$70 million
Project Completion
February 2011: Basement, 1st, 2nd and 4th floors
June 2011: 3rd floor
Project Schedule
Design: July 2007 - Feb 2009
Construction: January 2009 - December 2010
Construction of 3rd floor: September 2010 - April 2011
Building Start-Up/Furnishing/Equipment: December 2010 - February 2011
Building Start-Up of 3rd floor: April 2011 - June 2011
Occupancy: February 2011 - March 2011