Campus Services Renovation Floor 2 and 3, LSC 13th Floor, B500 Ground Floor, and ED2 North 5th Floor


Project Overview

The project will consist of remodel projects in the Campus Services Building 2nd and 3rd floors, Building 500 Ground Floor, and Education 2 North 5th floor located on the Anschutz Medical Campus and Lawrence Street Center Building 13th Floor located on the downtown Campus.  The spaces will be renovated to accommodate an open office concept with new furniture.  The design work will be completed in one phase and construction will be done in two phases. Phase 1 will consist of Campus Services Building 3rd floor, Lawrence Street Center 13th floor, and Building 500 Ground floor. Phase 2 will consist of Campus Services Building 2nd floor and Education 2 North 5th floor.

Project Manager

Dan Argersinger 303-724-5681

Project Architect/ Engineer

Page Southerland Page/RMH Group

General Contractor

Saunders Construction Inc.

Gross Square Footage

55,259

Project Cost

$8,085,445

Project Completion

December 2016

Project Schedule

Design – December 2016 to April 2016
Construction –April 2016 to December 2016