Project Overview
The 12,025 square foot facility provides health and safety support to the Research Enterprise on the Anschutz Medical Campus. EHS 2 is comprised of 7,356gsf on one level for waste-handling facilities to support CU Anschutz Medical Campus academic facilities. The support facility is a facility for the purpose of packaging, shipping and limited treatment of process waste/materials at the Anschutz Medical Campus.
The facility includes processing and holding space for campus waste. Space components include process waste storage areas and related building support space. The total project cost for EHS 2 was $2.1 million. EHS 2 was designed by LOA Architects based on a design-bid-build construction method. Construction was completed in February 2007.
View Project Site Map (PDF)
Project Manager
Dan Shomers, 303-724-1245
Project Architect
LOA Architecture
General Contractor
Golden Triangel
Gross Square Footage
12,025/ 7,356
Project Cost
$3.2 million/ $2.1 million
Project Completion
April 2004/ February 2007