Barbara Davis Center for Childhood Diabetes


""

Project Overview

The Barbara Davis Center for Childhood Diabetes' core and shell and 1st and 4th floors were completed in March 2005. Phase 3, with the fit-out of the 2nd and 3rd floors, was completed in October 2007. The 2nd floor houses clinical research and the 3rd floor houses laboratory research space. The total project cost of all phases is $29.4 million. The designed square footage is 112,000 gsf.

View Project Site Map (PDF)

 

Project Manager

Doug Derber, 303-724-1032

Project Architect

AndersonMasonDale Architects

General Contractor

JE Dunn

Gross Square Footage

112,000

Project Cost

$29.4 million

Project Completion

October 2006

Project Schedule

Design Phase 1-2

Design Phase 3: July 2002 – Jun 2004

Construction Phase 1-2: March 2006 - August 2007

Construction Phase 3

  • Building Start-Up/Furnishing/Equipment Phase 1-2: August 2007 - December 2007
  • Building Start-Up/Furnishing/Equipment Phase 3

Occupancy Phase 1-2: January 2008