Business School Infill Phase 2


Project Overview: 
The proposed project is a three-story infill of the Business School courtyard that includes new construction as well as renovations to some areas of the existing building to support the infill space.
Project Manager
Sharon Anthony 303-724-1155
 
General Contractor
JE Dunn Construction Company
 
Gross Square Footage
15,300 square feet
Project Cost
$8 Million Plus
Project Completion
December 2019
Project Schedule
Design: February 2018 – December 2018
 
Construction: November 2018 – December 2019