B400 Series Electrical Upgrade



Project Overview

Install new medium voltage cable including excavation in Buildings 400, 401, 402, 406, and 407 on the Anschutz Medical Campus. Five pad-mounted S&C switchgear will be added so as to strategically close or open switches to isolate building if there is a load or failure problem. This will allow greater redundancy in operating the electrical service for the buildings. Hi-pot testing of all new circuits will be included. 

Project Managers

Dan Argersinger – Facilities Management Projects daniel.argersinger@ucdenver.edu

Project Architect/ Engineer

RMH Group 

General Contractor

TBD

Gross Square Footage

115,613

Project Cost

$482,336

Project Completion

April 2020

Project Schedule

Design:  March 2019 – August 2019

Construction:  August 2019 – March 2020​

 ​