Project Overview
The Barbara Davis Center for Childhood Diabetes' core and shell and 1st and 4th floors were completed in March 2005. Phase 3, with the fit-out of the 2nd and 3rd floors, was completed in October 2007. The 2nd floor houses clinical research and the 3rd floor houses laboratory research space. The total project cost of all phases is $29.4 million. The designed square footage is 112,000 gsf.
View Project Site Map (PDF)
Project Manager
Doug Derber, 303-724-1032
Project Architect
AndersonMasonDale Architects
General Contractor
JE Dunn
Gross Square Footage
112,000
Project Cost
$29.4 million
Project Completion
October 2006
Project Schedule
Design Phase 1-2
Design Phase 3: July 2002 – Jun 2004
Construction Phase 1-2: March 2006 - August 2007
Construction Phase 3
- Building Start-Up/Furnishing/Equipment Phase 1-2: August 2007 - December 2007
- Building Start-Up/Furnishing/Equipment Phase 3
Occupancy Phase 1-2: January 2008